Interactive demo
See exactly what your owners receive on Friday.
Watch the 90-second product tour, then scroll through a full three-page Weekly Stakeholder Report. Every pixel is the same code path that runs in production.
The deliverable
Friday Weekly Stakeholder Update.
Sample data for a fictional medical-center project. Real owners receive this via magic link, can download a PDF on demand, and sign off without ever creating an account.
General Contractor
Halverson & Reed
Builders — Est. 1962
Owner / Client
Northpoint Capital
Real Estate Partners
Weekly Stakeholder Report
Meridian Harbor Tower
Phase II
Project Team
GC Internal Team
- Project ManagerD. Okafor
- SuperintendentR. Delacroix
- Asst. Project ManagerM. Sato
- Project EngineerE. Vasquez
- Project CoordinatorH. Lindqvist
Owner / Representative
- Owner's RepJ. Marchetti
- Development ManagerS. Braun
Architect & Design
- Architect of RecordKaufmann Hale
- Structural EngineerThornton Bryce
- MEP EngineerAtelier Koizumi
Schedule
On Track — Day 143 / 190
Day 143 / 190 — 47 working days to substantial completion.
% Complete
63%
+2 percentage points vs. 61% planned.
Weekly Update
This Week
- 01Completed formwork installation, Level 4 slabGrid A–D
- 02Stripped & re-shored Level 3 slab; QA inspection passedACI
- 03MEP rough-in walkthrough with Atelier Koizumi, Levels 2–3Accepted
- 04North-elevation curtain wall mock-up installed (Unit 2B)Mock-up
- 05Tower crane quarterly hook & cable inspectionPassed
- 06Skid arrival: fire pump, jockey pump, emergency generatorB1
- 07Owner walk — Level 2 hospitality shell & coreThu Apr 24
- 08Closed 11 RFIs; submitted 4 (envelope, façade, slab edge)RFI Log
- 09Below-grade waterproofing inspection — south wallClosed
- 10Zero recordable incidents · 1,420 manhours workedSafety
Next Week
- 01Level 4 slab concrete pour — 6AM start, full closureWed Apr 29
- 02Level 5 column formwork & rebar placement beginsFri May 1
- 03Envelope installation kickoff — east elevation, zones 1–2Façade
- 04B1 main switchgear set & energization coordinationMEP
- 05Mechanical rough-in start, Level 4 (upon slab release)MEP
- 06Design coordination: Level 3 lobby finishes & stoneTue
- 07Revised 3-week lookahead & resource histogram issuedSchedule
- 08Sprinkler main riser install — risers 2 & 3FP
Open Constraints
Structural steel delivery — 5-day delay impacting Level 5 start
Mill shipment re-routed via Tacoma; compression of framing sequence under review with erector. Recovery plan submitted Apr 20; awaiting Owner acknowledgment before crew ramp-up.
Electrical gear lead time — 2 weeks beyond baseline
Switchgear vendor confirmed revised ship date of May 18. Evaluating temporary service strategy for commissioning window; impact to B1 MEP start being quantified.
Curtain wall unit pricing — ASI 014
Architect issued ASI 014 modifying mullion depth at corner conditions. Pricing returned; change order package with Northpoint for approval.
Permit: B1 mechanical room separation rating
Pending AHJ clarification on 2-hour rating at generator pad. Site review scheduled week of May 4.
Field Photography
01 / 06
Level 3 slab — post-pour, looking north
02 / 06
North-elevation curtain wall mock-up (Unit 2B)
03 / 06
B1 generator set staging & fire pump skid
04 / 06
Tower crane hook inspection — quarterly
05 / 06
Core wall rebar placement, Level 4
06 / 06
Owner walk — Level 2 hospitality shell